A "Scrum of Scrums"meeting is:

  1. Another name for the daily standup project meeting in a Scrum team.
  2. Amechanism that coordinates multiple teams working on a single project.
  3. Aproject meeting that happens twice every day across the Scrum teams.
  4. An occasional leadership meeting that provides direction to multiple Scrum teams.

Answer(s): B



What is the best description of the relationship between Scrum andextremeProgramming(XP)?

  1. XP is a component of Scrum.
  2. The principles of each are often complementary.
  3. Scrum is a component of XP.
  4. The principles of each are often contradictory.

Answer(s): B



Risk exposure is the:

  1. Funds set aside to contain the risk.
  2. Probability a risk will occur.
  3. Amount of money the risk will cost if it occurs.
  4. Amount of damage to the project if the risk occurs.

Answer(s): A



Agile communication is effective because:

  1. release and iteration planning keep team members aligned, daily synchronization eliminates confusion, and iteration demonstrations keep the team focused on deliverables.
  2. Agile communication methods focus on detailed, written requirements and specifications that are more complete and allow the team to manage change more effectively.
  3. the use of charts and diagrams over written reports creates clear, targeted communication, and customer involvement in monthly reviews eliminates changes in requirements.
  4. daily iteration planning allows change to be managed, and weekly standup meetings ensure that impediments are quickly identified and effectively managed or removed.

Answer(s): A