A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

  1. Number of requirements tested and approved
  2. Distribution of project changes
  3. Requirements status during the project development cycle
  4. Number of requirements approved vs. number of requirements rejected

Answer(s): A



The business analyst wishes to clarify the project’s key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

  1. How is the organizational chart structured?
  2. What is the business need?
  3. Which functional areas are impacted?
  4. Which stakeholders have the most influence?

Answer(s): B



A business analyst captures an application’s current limitations and consults with end users to identify new features for the next version. What can be used to analyze this information and determine project scope?

  1. Root cause analysis
  2. Capability table
  3. As-is process
  4. Requirements traceability matrix

Answer(s): C


Reference:

https://www.lucidchart.com/blog/as-is-process-analysis



A key component of the business analyst’s role during acceptance testing is to:

  1. delegate execution of acceptance testing and defect identification to users.
  2. execute all acceptance tests on behalf of the user community.
  3. act as a resource only when users encounter difficulties while performing tests.
  4. assist the quality assurance department by defining acceptance criteria.

Answer(s): C


Reference:

https://www.businessanalystlearnings.com/blog/2015/10/21/the-role-of-business-analysts-in-user-acceptance-test-sessions-how-to-identify-test-cases



Page 12 of 51



Post your Comments and Discuss PMI PMI-PBA exam with other Community members:

Sultan commented on September 23, 2023
Q- 91(During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product’s functions and requirements. The business analyst struggles with facilitating the group to reach an agreement. What should the business analyst have defined to avoid this? The correct answer is A NOT B. Because here we are taking about BA not PM.
Anonymous
upvote