Free PMI-PBA Exam Braindumps (page: 20)

Page 20 of 51

The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

  1. Requirements baseline document
  2. Requirements management plan
  3. Requirements impact analysis
  4. Requirements traceability matrix

Answer(s): A



A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

  1. let the users decide if the test result is acceptable.
  2. change the requirement according to the test result.
  3. verify that the test case is incorrect.
  4. ask the tester to perform the test again.

Answer(s): C



A project that was ongoing well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

This could have been avoided if:

  1. the customer met with regulatory authorities to verify that their requirements were also considered.
  2. a change control process for requirements and their statuses was followed.
  3. the project manager circulated the meeting minutes after the discussions with all the attendees.
  4. the project team documented customer requests and obtained sign-off.

Answer(s): D



Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.

In which reference material can the business analyst find information about the missing project stakeholders?

  1. Business analyst communication plan
  2. Business case
  3. Organizational chart
  4. Business analysis plan

Answer(s): A



Page 20 of 51



Post your Comments and Discuss PMI PMI-PBA exam with other Community members:

Sultan commented on September 23, 2023
Q- 91(During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product’s functions and requirements. The business analyst struggles with facilitating the group to reach an agreement. What should the business analyst have defined to avoid this? The correct answer is A NOT B. Because here we are taking about BA not PM.
Anonymous
upvote