Free PMI-RMP Exam Braindumps


  • Exam Code: PMI-RMP
    Exam Title: PMI Risk Management Professional
  • Exam Provider: PMI
  • Exam Questions: 443
  • Updated On: 2-Feb-2025
QUESTION: 1
Lisa is the project manager of the SQL project for her company. She has completed the risk
response planning with her project team and is now ready to update the risk register to reflect
the risk response. Which of the following statements best describes the level of detail Lisa
should include with the risk responses she has created?

A. The level of detail is set by historical information.
B. The level of detail should correspond with the priority ranking.
C. The level of detail must define exactly the risk response for each identified risk.
D. The level of detail is set of project risk governance.

Answer(s): B

QUESTION: 2
Jenny is the project manager for the NBT projects. She is working with the project team and
several subject matter experts to perform the quantitative risk analysis process. During this
process she and the project team uncover several risks events that were not previously
identified.
What should Jenny do with these risk events?

A. The events should be entered into qualitative risk analysis.
B. The events should be determined if they need to be accepted or responded to.
C. The events should be entered into the risk register.
D. The events should continue on with quantitative risk analysis.

Answer(s): C

QUESTION: 3
You work as the project manager for Bluewell Inc. Your project has several risks that wil affect
several stakeholder requirements. Which project management plan will define who wil be
available to share information on the project risks?

A. Risk Management Plan
B. Stakeholder management strategy
C. Resource Management Plan
D. Communications Management Plan

Answer(s): D

QUESTION: 4
You work as a project manager for BlueWell Inc. Your project is using a new material to
construct a large warehouse in your city. This new material is cheaper than traditional building
materials, but it takes some time to learn how to use the material properly. You have
communicated to the project stakeholders that you will be able to save costs by using the new
material, but you wil need a few extra weeks to complete training to use the materials. This risk
response of learning how to use the new materials can also be known as what term?

A. Team development



Post your Comments and Discuss PMI PMI-RMP exam with other Community members:

PMI-RMP Discussions & Posts