The project manager is reviewing a project's progress and notices that one of the risks has become an issue.
What should the project manager do to address the situation?

  1. Initiate a change request to obtain additional funds from the management reserve
  2. Meet with the project team and customer to brainstorm about potential solutions
  3. Schedule a high-priority meeting with the project stakeholders to discuss the issue
  4. Collaborate with the relevant stakeholders on implementing the risk response plan

Answer(s): D



A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?

  1. During the planning phase, when processes for scope definition and activity duration and sequencing will be performed
  2. Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated
  3. In the initiation process, as it happens concurrently with the project contract and project charter creation
  4. As soon as possible, as project delays can be significantly avoided when a schedule is developed early

Answer(s): A



After conducting a performance assessment, the project manager identified that some gaps still exist.
What should the project manager ensure?

  1. Awards are given to all team members for playing a role in the project and undertaking the assessment.
  2. Performance improvement programs are organized for all team members who were assessed.
  3. All team members rotate their job schedules immediately to make them versatile.
  4. Assessment results are kept private and not shared among team members.

Answer(s): B



A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested.
What should the project manager do next?

  1. Discuss the changes with the client and jointly make the decision on how to proceed.
  2. Reject the changes and stay the original course as initially agreed with the client.
  3. Review the risk register to see if mitigations have already been outlined for this scenario.
  4. Review the changes and make the decision based on the project team's recommendations.

Answer(s): A