A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for
2 days.
What does the project manager need to do now?

  1. Inform the product owner
  2. Inform the project sponsor
  3. Inform the relevant stakeholders
  4. Inform the project team only

Answer(s): C



A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team.
What should the project manager do?

  1. Ask the team member to bring up the concern in the next daily meeting
  2. Send an email explaining the issue to all team members
  3. Reassign the task to another team member
  4. Move the task to the next sprint

Answer(s): A



A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?

  1. Help the teams in establishing and adhering to their ground rules and revisit after regular intervals
  2. Copy the ground rules established by another project and provide them to the teams
  3. Establish the team ground rules and share them with the team for strict adherence
  4. Extract the organization's policies and processes, customize them, and give them to the teams to adhere to

Answer(s): A



An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?

  1. Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend
  2. Escalate to management that the agile process is not going to work and ask them to speak to the agile coach
  3. Have a discussion with the team on the approach and come to a decision on when the daily standups should be
  4. Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team

Answer(s): C