You are the project manager of the HJU project for your company. This project will last for 18 months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change request that will likely have an impact on the project costs and schedule. Robert assures you that he will pay for the extra time and costs associated with the risk event. You tell Robert that the change request may affect more areas of the project than just time and cost and that you are worried about the additional risks the change request will bring. What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?

  1. Project change control system
  2. Integrated change control
  3. Risk analysis
  4. Configuration management

Answer(s): B



Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

  1. She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
  2. She can filter all risks based on their affect on schedule versus other project objectives.
  3. She can have the project team pad their time estimates to alleviate delays in the project schedule.
  4. She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.

Answer(s): A



Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe. What type of risk response has Adrian used in this example?

  1. Avoidance
  2. Mitigation
  3. Acceptance
  4. Transference

Answer(s): D



Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?

  1. Transference
  2. Avoidance
  3. Contractual
  4. Mitigation

Answer(s): A



Page 33 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote