You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the quantitative risk analysis process.
Which one of the following is NOT a valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

  1. You will use organizational process assets for risk databases that may be available from industry sources.
  2. You will use organizational process assets for studies of similar projects by risk specialists.
  3. You will use organizational process assets to determine costs of all risks events within the current project.
  4. You will use organizational process assets for information from prior similar projects.

Answer(s): C



Which of the following processes looks at the complex web of actors, rules, conventions, processes, and mechanisms concerned with how relevant risk information is collected, analyzed and communicated, and how management decisions are taken?

  1. Risk Communication
  2. IRGC
  3. Risk Response Planning
  4. Risk Governance

Answer(s): D



You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

  1. 1.06
  2. 0.92
  3. -$30,647
  4. 0.93

Answer(s): D



You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your project. One of the project risks has a 50 percent probability of happening, and it will cost the project $55,000 if the risk happens. What will be the expected monetary value of this risk event?

  1. Negative $27,500
  2. Zero - the risk event has not yet occurred
  3. Negative $26,000
  4. Negative $55,000

Answer(s): A



Joyce is the project manager for her company. Joyce and her project team are working through the quantitative analysis for certain risk events within her project. According to the enterprise environmental factors the project manager is to perform sensitivity analysis on any risk with an impact greater than $5,000 in the project. What is the sensitivity analysis?

  1. It determines which risk events have the most potential impact on the project.
  2. It uses round of anonymous surveys to predict which events are most likely to happen.
  3. It uses rounds of anonymous surveys to predict probability and impact.
  4. It determines possible combinations of risk events to predict overall project success, failure, or probability of achieving project objectives.

Answer(s): A



Viewing page 35 of 90
Viewing questions 171 - 175 out of 273 questions