Your organization has named you the project manager of the JKN Project. This project has a BAC of
$1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?
- Project risks will increase.
- The project will take longer to complete, but risks will diminish.
- Project costs will increase.
- The amount of hours a resource can be used will diminish.