What approach can a project manager use to improve the project's performance during qualitative risk analysis?

  1. Focus on near-term risks first.
  2. Create a risk breakdown structure and delegate the risk analysis to the appropriate project team members.
  3. Focus on high-priority risks.
  4. Analyze as many risks as possible regardless of who initiated the risk event.

Answer(s): C



You are the project manager of the NHH project for your company. You and the project team have completed the quantitative risk analysis for your project. During this process you create a contingency reserve based on the risk probability-impact matrix as seen in the figure below.


Based on the information in the figure above, what amount would you need to include in your risk contingency fund?

  1. -$465,000
  2. $171,500
  3. -$258,500
  4. $258,500

Answer(s): D



Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?

  1. Risk management plan
  2. Project sponsor
  3. Risk response plan
  4. Look-up table

Answer(s): D



The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

  1. They are the individuals that will need a sense of ownership and responsibility for the risk events.
  2. They are the individuals that will have the best responses for identified risks events within the project.
  3. They are the individuals that are most affected by the risk events.
  4. They are the individuals that will most likely cause and respond to the risk events.

Answer(s): A



You are the project manager for the NHQ Project. This project requires that you install 140 copies of design software onto your department's computers. The vendor offers you a twenty percent discount on the software if your company will purchase 150 or more copies of the software. You communicate this offer with other departments in your firm to see if anyone else would need 10 copies of the software to save your project a significant amount of funds. What is this risk response called?

  1. Exploiting
  2. Avoidance
  3. Sharing
  4. Transference

Answer(s): C



Viewing page 45 of 90
Viewing questions 221 - 225 out of 273 questions