B. Balanced matrix
C. Piojectized
D. Strong Matrix

Answer(s): B
Explanation:
Balanced matrix: Power is shared between both Functional and Project Manager. In this
case you include the functional manager in the meeting therefore it is Balanced matrix
organization.
QUESTION: 12
You have been with the organization; you constantly hear rumours about a certain
CAPM failing to live up to the CAPM Code. What you should do?

A. You can gather as much information as you can before proceeding
B. Confront the person immediately
C. Ignore the rumours
D. ^ass the rumours along

Answer(s): A
Explanation:
You can gather as much information as you can before proceeding.
QUESTION: 13
Who is responsible for issuing the project charter?

A. The project manager
B. The project sponsor
C. The Team lead
D. The nianagement

Answer(s): B
Explanation:
The project sponsor creates and issues the project charter.
QUESTION: 14
In PMBOK, the seller is ________ to the project team.

A. Internal
B. External
C. Outside
D. Assigned

Answer(s): B
Explanation:
In PMBOK, the seller is External to the project team.