Which process can take place during a release review workshop?

  1. Controlling a stage
  2. Managing product delivery
  3. Managing a stage boundary
  4. Directing a project

Answer(s): B



Which BEST describes the senior user role when tailoring the organization theme?

  1. An ‘agile sponsor’
  2. An ‘executive sponsor’
  3. A ‘coach’
  4. A ‘super product owner’

Answer(s): D


Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_52



What term is used to describe boards that display what work needs to be completed for people working on a project?

  1. Work in progress limit
  2. Information radiator
  3. Highlight report
  4. Glad! Sad! Mad!

Answer(s): C


Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&expandNav=true



Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.

  1. 1 and 2
  2. 2 and 3
  3. 3 and 4
  4. 1 and 4

Answer(s): B