What should the business case state about the minimum viable product (MVP)?

  1. When the MVP will be defined
  2. That the MVP must go into operational use
  3. What the MVP is
  4. That the MVP is the same as project viability

Answer(s): B


Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_56&showNav=true&expandNav=true



How does the change theme regard change in PRINCE2 Agile?

  1. As disruptive
  2. As something to be avoided
  3. As a necessity
  4. As inevitable

Answer(s): D


Reference:

https://edward-designer.com/web/prince2-foundation-notes-change-theme/



Which statement about the ‘keep teams stable’ target is CORRECT?

  1. It applies primarily to the long term, such as a project or a program
  2. It is the primary reason why the tolerance for cost is set to zero
  3. It prevents compromising the overall quality level of the product
  4. It results in the early delivery of a minimum viable product

Answer(s): B


Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41



What needs to happen when new detailed requirements are added to a timebox?

  1. Requirements of a similar level of effort should be removed
  2. More people should be added to the delivery team
  3. The delivery milestones should be reviewed and re-planned
  4. Formal change control should be applied

Answer(s): A