Which of the following is NOT within the authority of the Project Board?

  1. Approve the End Project Report
  2. Set Stage-level tolerance
  3. Approve Stage Plans
  4. Set project-level tolerance

Answer(s): D



Which of the following is a Project Board control?

  1. Project-level tolerance
  2. Stage-level tolerance
  3. Checkpoint Report
  4. Quality Register

Answer(s): B



Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?

  1. Project Manager
  2. Project Board
  3. Team Manager
  4. Corporate or programme management

Answer(s): B



There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

  1. Initiation as the first stage, the remainder of the project as the second stage
  2. Initiation as the first stage, closure activities as the second stage
  3. Procurement as the first stage, design and implementation as the second stage
  4. Pre-project work as the first stage, initiation as the second stage

Answer(s): A