What is the name given to an individual who is responsible for the management, monitoring and control of all aspects of a particular risk assigned to them?

  1. Risk Actionee
  2. Risk Coordinator
  3. Project Risk Manager
  4. Risk Owner

Answer(s): D



What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?

  1. Risk Manage
  2. Risk Coordinator
  3. Risk Actionee
  4. Risk Owner

Answer(s): C



Which of the following is TRUE regarding risk?

  1. A Risk Register contains details of the risk management techniques and standards to be applied
  2. The PRINCE2 risk management procedure consists of five iterative steps: Identify, Assess,
    Plan, Implement, Communicate
  3. A Risk Management Strategy is produced by a risk owner
  4. PRINCE2's approach to risk does not involve stakeholders

Answer(s): A



Which of the following is NOT one of the five risk management procedure steps?

  1. Assess
  2. Identify
  3. Plan
  4. Register

Answer(s): D