In what process is the authorization to deliver the project's products given?

  1. Starting up a Project
  2. Initiating a Project
  3. Managing a Stage Boundary
  4. Directing a Project

Answer(s): D



Which of the following is NOT part of quality planning?

  1. Define quality responsibilities
  2. Gain acceptance of the project product
  3. Agree acceptance criteria
  4. Set quality tolerances

Answer(s): B



Which should be provided by a project mandate?

  1. Terms of reference
  2. Detailed Business Case
  3. Stage tolerances
  4. Initiation Stage Plan

Answer(s): A



Which is an objective of the Starting up a Project process?

  1. Identify who will be responsible for creating the Project Plan
  2. Agree how the project will be monitored and controlled after initiation
  3. Authorize the Project Manager to proceed with the initiation stage
  4. Agree how issues and changes will be identified, assessed and controlled

Answer(s): A