Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  1. Principles
  2. Processes
  3. Tailoring PRINCE2 to the project environment
  4. Themes

Answer(s): A



Which should be funded by a change budget?

  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities

Answer(s): A



Which of the following describes a use of a Configuration Item Record?

  1. Define the identification scheme to be applied to the project
  2. Identify the techniques and procedures required within the Work Package
  3. Record the change in a product's status
  4. Record the reporting requirements for the Work Package

Answer(s): C



Which characteristic distinguishes a project from regular business operations?

  1. Produces benefits
  2. Introduces business change
  3. Manages stakeholders
  4. Incurs cost

Answer(s): B



What process aims to ensure accurate progress information is provided to the Project Manager?

  1. Starting up a Project
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project

Answer(s): C



Viewing page 7 of 50
Viewing questions 31 - 35 out of 244 questions



Post your Comments and Discuss PRINCE2 PRINCE2-Re-Registration exam dumps with other Community members:

PRINCE2-Re-Registration Exam Discussions & Posts

AI Tutor 👋 I’m here to help!