Which of the following document will be required as a source of input when considering a list of possible risks?

  1. Product documentation
  2. Project documentation
  3. Historical Information
  4. All of the above

Answer(s): D



In a traditional waterfall methodology, most risk management activity occurs close to milestone

  1. True
  2. false

Answer(s): A



In a spiral development model the risk management activity falls in the explicit risk management portion.

  1. True
  2. false

Answer(s): A



Risk management is an independent auditing process.

  1. True
  2. False

Answer(s): B



Risk should be the sole responsibility of project manager.

  1. True
  2. False

Answer(s): B