Free SAP C_ACTIVATE12 Exam Questions (page: 3)

What is the purpose of a firm-up sprint?

  1. To revise the release plan and sprint plan
  2. To demonstrate functionality from previous sprints
  3. To perform string test
  4. To run an end-to-end integration test

Answer(s): C



What tool provides sizing estimators for the "system conversion" transition path?

  1. SAP best practices explorer
  2. Scope and effort analyser
  3. SAP Transformation navigator
  4. SAP readiness check

Answer(s): D



What is the minimum number of quality gates mandated by the SAP Activate methodology?

Please choose the correct answer.

Response:

  1. 0
  2. 3
  3. 4
  4. 5

Answer(s): C



Which content packages are available in the SAP Package Library?

There are 2 correct answers to this question.

Response:

  1. SAP Activate Methodology
  2. SAP Best Practices
  3. Solution Builder
  4. Rapid Deployment Solutions

Answer(s): B,D