Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?
Note: There are 3 correct answers to this question

  1. Adjusted transportation receipts
  2. Aggregated constraints
  3. Maximum lot size
  4. Transportation lead time
  5. Minimum lot size

Answer(s): A,D,E



You are reviewing the master data types that are often used for supply and inventory planning.
Which master data types are compound master data types?
Note: There are 2 correct answers to this question

  1. SOURCEPRODUCTION
  2. SOURCECUSTOMER
  3. SOURCELOCATION
  4. SOURCECUSTGROUP

Answer(s): B,C



Which options can be used to reduce the runtimes of a time-series optimizer run?
Note: There are 3

correct answers to this question.

  1. Keep the number of fairshare segments small
  2. Split into multiple planning areas to support weekly vs. daily planning needs.
  3. Use non-overlapping networks by using Subnetworks ID maintained at Location-Products to reduce the size of the problem
  4. Eliminate the usage of telescopic time buckets
  5. Increase the use of incremental lot size beyond the frozen horizon.

Answer(s): A,C,D



What is an example of a commonly used time-independent key figure?

  1. A Special key figure marked as an aggregate key figure (aggregate constraint)
  2. A unit of measure key figure, such as UoM Conversion Factor
  3. Any attribute as a key figure
  4. A currency conversion key figure, such as Exchange Rate

Answer(s): C