Which processing stage refers to “Stock posting completed”?

  1. SPCD
  2. SPCL
  3. SPCO
  4. SPST

Answer(s): A



During inspection planning, you cannot access different master data.

  1. Incorrect
  2. Correct

Answer(s): A



Which statements are correct? (More than one answer is true.)

  1. An inspection lot can be created automatically or manually.
  2. Results recording cannot be carried out after the sample size has been determined.
  3. When the indicator “QM procurement active” is set, quality management in procurement is activated for all plants of a client.
  4. Details for the QM specific procurement processes as plant level are determined using the QM control key.

Answer(s): A,D



You can monitor the receipt of a quality certificate with and without inspection lot processing, independently of the time of goods receipt.

  1. Correct
  2. Incorrect

Answer(s): A



You can assign follow-up actions to the codes in the code groups of the task catalog.

  1. Incorrect
  2. Correct

Answer(s): B