Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question

  1. Document information records
  2. Internally processed activities
  3. Basic dates for activities
  4. Material components
  5. Relationships

Answer(s): B,D,E



Material

How can the system activate requirements (such as reservations or purchase requisitions)?

Note: There are 2 correct answers to this question

  1. Immediately, by saving the project
  2. Automatically, using the requirement date and the replenishment lead time
  3. Using a standard milestone activity
  4. When releasing a network or an activity

Answer(s): B,D



Material

Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement

scheduling of events.

What is the requisites for implement scheduling of events?

  1. Priority of events must be set.
  2. Scheduling parameters for material scheduling must be set.
  3. Events must be released manually.
  4. Event scenarios must be defined.

Answer(s): D



Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

  1. Project versions can be changed
  2. Project versions are mandatory for Milestone Trend Analysis (MTA)
  3. Project versions can be created automatically based on user status
  4. Manually Created project versions always require a project version profile

Answer(s): B,C