The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.

  1. False
  2. True

Answer(s): A



For which objects can billing plans be created? Note: There are 2 correct answers to this question

  1. WBS elements
  2. Project definition
  3. Sales order items
  4. Milestones

Answer(s): A,D



Revenues & Payment

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

  1. Settle the WBS element to the highest billing element before you do the result analysis.
  2. Split the project intdifferent project according to each company code.
  3. Change the project structure so that it correspond better to the company's organization structure.
  4. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Answer(s): C



Cost & Budget.

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  1. Settlement rules
  2. Costing Sheet
  3. Investment profile.
  4. Results analysis key

Answer(s): A