During an inspection the lab technicians record the same test values for an inspection characteristic.
Which of the following do they assign to the products?

  1. As a sample size
  2. As an inspection point
  3. As a partial lot
  4. As a batch

Answer(s): B



Which object must combined in test scheduling in the stability study
Ther are 3 correct answer(s).

  1. Physical drawing procedure
  2. Strategy
  3. Initial sample
  4. Inspection plans
  5. Physical samples

Answer(s): B,D,E



Your customer uses MIC and requests automatic defect recording After configuration defect recording the implementation Guide ,which additional steps must you perform to satisfy customer requirements?
There are 2 correct answers.

  1. Select the radio button to activate quality notification in the defect class
  2. Assign a notification type to an inspection type
  3. Activate defects recording in the characteristic control indicator for your MIC
  4. ssign an inspection method to your MIC

Answer(s): B,C



Your business requirements demand production triggers.
Which of the following events in production can create an inspection lot(3 Correct Ans)

  1. Goods Movement
  2. Order Creation
  3. ATP check
  4. Dead line monitoring /batch monitoring
  5. Order Release

Answer(s): A,D,E



Your customer wants to add the quality score of a material as criterion for the vendor evaluation Where do you set the calculation procedure for the quality score:?

  1. Dud code
  2. Vendor master
  3. Quality info record in procurement
  4. Material master

Answer(s): A



Viewing page 2 of 17
Viewing questions 6 - 10 out of 80 questions



Post your Comments and Discuss SAP C_TS414_2021 exam prep with other Community members:

Join the C_TS414_2021 Discussion