The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?

  1. Use the reorder point.
  2. Use the minimum order quantity.
  3. Use the fixed lot size procedure.
  4. Use the MRP type for vendor managed inventory.

Answer(s): C



Why would you use phantom assemblies?
Note: There are 3 correct answers to this question.

  1. To make the assignment of components easier
  2. To simplify the structure of bills of material
  3. To reduce the number of changes required in bills of material
  4. To increase the number of planning levels
  5. To reduce the number of material masters

Answer(s): A,B,C



Which bill of material (BOM) categories can you define in SAP S/4HANA?
Note: There are 2 correct answers to this question.

  1. Functional Location BOM
  2. Sales Order BOM
  3. Class BOM
  4. Work Center BOM

Answer(s): A,B



Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?
Note: There are 2 correct answers to this question.

  1. Run MRP with automatic selection of production version.
  2. Run PP/DS heuristics for repetitive manufacturing.
  3. Run MRP with quota arrangement.
  4. Assign planned orders manual lying the planning table.

Answer(s): B,C



MRP created a planned order for a material that has one single material from stock as a component.
What happens to this dependent requirement when you convert the planned order into a production order?

  1. It is converted into a production order.
  2. It is converted into a reservation.
  3. It is converted into a planned order.
  4. It is converted into a schedule line.

Answer(s): B