Free SAP C_TS422_1909 Exam Questions (page: 8)

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?
Note: There are 2 correct answers to this question.

  1. Run MRP with automatic selection of production version.
  2. Run PP/DS heuristics for repetitive manufacturing.
  3. Run MRP with quota arrangement.
  4. Assign planned orders manual lying the planning table.

Answer(s): B,C



MRP created a planned order for a material that has one single material from stock as a component.
What happens to this dependent requirement when you convert the planned order into a production order?

  1. It is converted into a production order.
  2. It is converted into a reservation.
  3. It is converted into a planned order.
  4. It is converted into a schedule line.

Answer(s): B



You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

  1. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
  2. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
  3. The previously dispatched operation stays as is the new operation is inserted after the dispatched operation.
  4. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.

Answer(s): B



In which data objects do you maintain the production line as the work center for repetitive manufacturing?
Note: There are 2 correct answers to this question.

  1. Production version
  2. Production cost collector
  3. Routing
  4. Repetitive manufacturing profile

Answer(s): A,C