SAP C_TS422_2022 Exam
SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (Page 3 )

Updated On: 7-Feb-2026

You want to schedule an operation finitely, without removing other operations.
Which scheduling strategy do you select?

  1. Insert operation
  2. Squeeze in
  3. Schedule in working time only
  4. Find Slot

Answer(s): D



When you create a sales order.
When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?

  1. When MRP creates a dependent requirement
  2. When MRP creates a planned order
  3. When you create a sales order
  4. When MRP creates a planned order

Answer(s): C



What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

  1. The planned order is converted to a production order.
  2. The planned order's component availability is checked.
  3. The planned order generates capacity requirements
  4. The planned order's components are copied to the picking list.

Answer(s): C



During production order creation, several valid production versions are found. How does the system choose the production version?

  1. Lot size or material cost
  2. Validity period or sales order
  3. Planned order or material number
  4. Alphanumeric or quota arrangement

Answer(s): D



What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.

  1. Installation point
  2. Item type
  3. Quantity
  4. Scrap percentage

Answer(s): A,C