Which planning strategies can you use in the capacity scheduling table?

Note: There are 2 correct answers to this question.

  1. Scheduling control > Find slot
  2. Planning mode > Bucket
  3. Scheduling control > Close gap
  4. Planning mode > Order priority

Answer(s): A,B



Which operations are considered in the capacity scheduling table?

Note: There are 2 correct answers to this question.

  1. Only bottleneck operations
  2. Sub-operations
  3. Operations assigned to a pacemaker work center
  4. All operations

Answer(s): A,B



Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.

  1. Production orders
  2. Planned orders (firmed)
  3. Planned orders (unfirmed)
  4. ATP quantities

Answer(s): A,B



In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run?
Note: There are 2 correct answers to this question.

  1. Use a specific MRP list.
  2. Use a specific material status.
  3. Use a specific material group.
  4. Use a specific MRP type.

Answer(s): B,D



In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning.
What does this mean for the capacity requirements of a new order?

  1. MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.
  2. MRP creates the capacity requirements without considering existing load on the work centers.
  3. MRP creates the capacity requirements at the earliest possible time.
  4. MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Answer(s): A