How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.

  1. By capacity planning
  2. By order confirmation
  3. By order release
  4. By mass processing

Answer(s): C,D



For a production version to be valid consistent what requirements must be fulfilled?
Note: There are 3 correct answers to this question.

  1. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
  2. The consistency check must be performed.
  3. The assigned routing bill of material (BOM) must be valid in the entire validity period.
  4. The assigned routing bill of material (BOM) must have the same validity period.
  5. The lot size range must be within the lot size range of the assigned routing.

Answer(s): A,C,E



You want to use capacity availability checks for production orders.
Which settings have to be made for this?

Note: There are 2 correct answers to this question.

  1. The Relevant for Finite Scheduling indicator must be set.
  2. The scope of check must be defined in Customizing.
  3. A checking rule must be assigned to the work centers.
  4. An overall profile must be assigned in the checking control.

Answer(s): A,D



Which business processes are affected by settings in the order type dependent parameters?
Note:
There are 2 correct answers to this question.

  1. Schedule production orders.
  2. Check material availability.
  3. Select master data.
  4. Define integration with cost accounting.

Answer(s): C,D



For production orders cost object controlling (COC) can be carried out on an order related or product related basis.
Which of the following do you have to consider?

Note: There are 2 correct answers to this question.

  1. Productrelated COC is used in manufacturing for coproducts.
  2. In productrelated COC all costs are debited credited to a product cost collector.
  3. In orderrelated COC individual production orders do NOT have cost segments.
  4. Orderrelated COC is beneficial in a flexible production environment.

Answer(s): B,D



Viewing page 6 of 19
Viewing questions 26 - 30 out of 87 questions