SAP C_TS462_1909 Exam
SAP Certified Application Associate - SAP S/4HANA Sales 1909 (Page 3 )

Updated On: 1-Feb-2026

Which steps must be completed to implement a new SAP Fiori tile for a specific evaluation? There are 3 correct answers to this question.

  1. Create the tile and assign it to the evaluation
  2. Create the exception report in the background system
  3. Define the required thresholds
  4. Create the tile and assign it to the KPI
  5. Create a new KPI

Answer(s): A,C,E



Your customer wants to ship as much material as possible on a requested date and does NOT want any subsequent deliveries in case of shortage. What do you set to achieve this requirement? Please choose the correct answer.

  1. The "Complete delivery" indicator in the sales order header
  2. The "Only complete delivery (per item) allowed" indicator
  3. The "One delivery with quantity greater than zero has to be created" indicator
  4. The "No limit to subsequent deliveries" indicator

Answer(s): C



How often does SAP HANA create a save point? Please choose the correct answer.

  1. Every few seconds
  2. Every 30 minutes
  3. Every few hours
  4. Every few minutes

Answer(s): D



What activity is supported by the Sales Order Fulfillment Monitor? Please choose the correct answer.

  1. Change KPI data for sales
  2. Create sales contracts
  3. Resolve incomplete data
  4. Track warehouse orders

Answer(s): C



What is used to determine a pricing procedure? There are 3 correct answers to this question.

  1. Sold-to party
  2. Sales area
  3. Sales document type
  4. Item category
  5. Ship-to party

Answer(s): A,B,C