QUESTION: 1
What is required before you can create a multi-level material cost estimate without quantity
structure?

A. Material master with costing view
B. Specific valuation variants for material costings without quantity structure
C. Material master with accounting view and with MRP views
D. Specific costing variants for material costings without quantity structure

Answer(s): A
QUESTION: 2

Which settings can you configure per order type for the budget and availability control? There
are TWO correct answers for this question

A. Design budget manager
B. Budgeting on cost element level
C. Budget tolerance limits
D. Budget data entry layout

Answer(s): B, C
QUESTION: 3

Which object do you have to assign the cost component structure to?

A. Costing type
B. Costing variant
C. Valuation variant
D. Material master record

Answer(s): B
QUESTION: 4

Which objects can you plan in cost center accounting? There are THREE correct answers for
this question

A. Non-operating expense accounts
B. Activity prices
C. Secondary cost accounts
D. Statistical key figures
E. Balance sheet accounts

Answer(s): A, C, D
QUESTION: 5

In an SAP S/4HANA system, you have two profit centers with the same profit center code and
the same validity period, but different names. What does this indicate about the configuration of
the profit centers?

A. They are defined in separate controlling areas
B. They are assigned to different functional areas
https://Xcerts.com
2

Get The Premium Version

Allbraindumps.com
 Test Questions PDF from Myitguides.com

 Test Questions PDF from Myitguides.com