SAP C_TS4CO_1909 Exam
SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates (SAP S/4HANA 1909) (Page 4 )

Updated On: 7-Feb-2026

You configured an overhead costing sheet that uses the quantity-based overhead approach to calculate the overhead amount. What is required for the amount to be calculated?

  1. Cost accounts with the option to record quantity
  2. Activity types with actual or plan quantities maintained
  3. Statistically figures with values for the period
  4. Settlement rules with valid receiver objects

Answer(s): B



A profit center standard hierarchy contains all profit centers that are assigned to which organizational unit?

  1. Controlling area
  2. Client
  3. Operating concern
  4. Plant

Answer(s): A



What do you need to define in order to report variable costs that refer to the cost component split in account-based CO-PA? There are TWO correct answers for this question

  1. A variable cost field in
  2. A calculation formula
  3. A cost splitting profile
  4. A price difference profile

Answer(s): A,C



Duringposting, from which object does the system first derive the profit center if the profit center is NOT directly assigned to a network activity?

  1. Dummy profit center
  2. Project definition
  3. Network header
  4. WBS element

Answer(s): C



What is the default option for planning profitcenter values in SAP S/4HANA?

  1. Profitability analysis planning
  2. Business planning and consolidation
  3. Management accounting planning
  4. Financial accounting planning

Answer(s): B






Post your Comments and Discuss SAP C_TS4CO_1909 exam prep with other Community members:

Join the C_TS4CO_1909 Discussion