After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).
Which of the following planning file entries for this material are set by the system?

  1. The BOM explosion and the NETPL planning indicator
  2. The BOM explosion indicator
  3. The BOM explosion, the NETCH, and the NETPL planning indicators
  4. The NETCH and NETPL planning indicators

Answer(s): C



Which option for selecting a routing exists when you create a production order?

  1. Automatic selection of a reference operation set
  2. Manual selection based on settings in the order type-dependent parameters
  3. Automatic selection based on the selection ID in the material master
  4. Manual selection based on the list of routings maintained in the material master

Answer(s): B



Which of the following statements about the planning functions available in SAP ECC is correct?

  1. Master production scheduling (MPS) refers to preferred planning of important materials.
  2. Material requirements planning (MRP) includes automatic capacity leveling.
  3. Long-term planning (LTP) is a long-term form of forecast planning.
  4. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.

Answer(s): A



Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

  1. Rescheduling the operation
  2. Posting the goods receipt for the production order
  3. Confirming the operation
  4. Setting the status technically complete (TECO)
  5. Reducing the order quantity

Answer(s): C,D,E



Which of the following situations occur when a production order is set to Technically Complete (TECO)? (Choose three.)

  1. The order and its operations receive the system status Locked (LKD).
  2. Reservations are deleted.
  3. Purchase orders for external operations or non-stock materials are deleted.
  4. The order is no longer relevant for Material Requirements Planning.
  5. Capacity requirements are deleted.

Answer(s): B,D,E