Your customer wants to see feasible receipt quantities in a "confirmed production" key figure in DP.

What do you have to do to fulfill this request?

  1. Implement PP/DS. Only finite scheduled PP/DS orders can be used with "collaborate into DP planning book" transaction.
  2. Implement SNP or PP/DS. The "release to demand planning" transaction with key figure copy has to be used.
  3. Implement GATP. Confirmed quantities can then be updated periodically via the internal BW into the different DP planning books.
  4. Implement SNP. Only SNP can interact with DP since the time series liveCache is required.

Answer(s): B



Which configuration rule can you use to set up InfoCubes and planning object structures?

  1. Group characteristics without an n:m relation and with few values into one dimension.
  2. Set characteristics with few values as "line item dimension".
  3. Reduce the amount of dimensions to increase the performance of an InfoCube.
  4. Group characteristics with many values into one dimension.

Answer(s): A



Which of the following is a valid function of the internal BW?

  1. It is only used to import historical data for DP. Reporting is executed using the external BW.
  2. It can be used to back up planning results from liveCache to the database.
  3. It is only used for DP. SNP and PP/DS do not use the internal BW.
  4. Planning results stored in liveCache are automatically replicated to the database of the internal BW.

Answer(s): B



How can you back up planning data to the internal BW?

  1. Create a VirtualProvider for the planning area and connect it to an InfoCube.
  2. Use transaction /SAPAPO/TSCUBE - Load Data from InfoCube.
  3. Create a DataSource for the planning area and connect it to a VirtualProvider.
  4. Create a DataSource for the planning area and connect it to an InfoCube.

Answer(s): D



Which of the steps described below do you need to perform when creating InfoObjects to set up a DP or SNP scenario?

  1. Set up characteristics and key figures for DP and SNP in the internal BW.
  2. Create hierarchies for characteristics.
  3. Define navigational attributes for SNP characteristics.
  4. Create fixable key figures as BW key figures.

Answer(s): A