What are some of the values of SAP Cloud ALM for implementation?

  1. Accelerated time to market
  2. Central cost and effort management
  3. NO additional cost of product
  4. Pre-delivered SAP Activate tasks
  5. Comprehensive document repository

Answer(s): C,D,E



In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?

  1. Prepare
  2. Explore
  3. Deploy
  4. Realize

Answer(s): D



What is Scrum of Scrums?

  1. Integration meeting among the various Scrum teams
  2. Alternative to regular Scrum process for smaller teams

  3. Mechanism for gathering and validating requirements
  4. Frequent inspection of code and configuration prior to quality gates

Answer(s): A



What is the purpose of a firm-up sprint?

  1. To revise the release plan and sprint plan
  2. To run an end-to-end integration test
  3. To demonstrate functionality from previous sprints
  4. To perform string test

Answer(s): D



What are the core capabilities in SAP Cloud ALM for implementation?

  1. Task management
  2. Custom code management
  3. Process management
  4. Portfolio management
  5. Test management

Answer(s): A,C,E