Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path?

  1. Reporting functional specifications
  2. User acceptance test-plan
  3. Functional specifications
  4. Functional test scenarios

Answer(s): B,D



Which enhancements to SAP Cloud ALM are planned for the future? Note:

  1. Process scope
  2. Product coverage
  3. Task coverage
  4. Functional scope

Answer(s): B,D



What do you do during an iterative approach to build a solution?

  1. Build the solution module by module
  2. Provide a working solution only at the end of the release
  3. Include frequent inspection check-points
  4. Deliver a prototype of the solution

Answer(s): C



What are the core capabilities in SAP Cloud ALM for operations?

  1. Operation automation
  2. Upgrade analysis
  3. License management
  4. Monitoring
  5. Event and alert management

Answer(s): A,D,E



What does SAP Activate recommend to keep team members informed and aligned?

  1. Daily status meeting with project manager
  2. Daily progress review meeting with sponsor
  3. Daily team stand-up meeting
  4. Daily e-mail status updates to project manager

Answer(s): C