Which statement is true about using a Program Kanban system

  1. All work is visualized, progress is continually tracked
  2. WIP limits are used to provide any needed buffers
  3. Work is pushed through the Kanban to ensure train capacity is utilized
  4. The board tracks features, dependencies and milestones

Answer(s): C



What is the best way for the Release Train Engineer to show progress of work in the cur-rent Program Increment (PI) to management?

  1. Conduct a System Demo
  2. Generate a velocity trend report
  3. Conduct a retrospective
  4. Arrange for a separate meeting with Business Owners

Answer(s): A



Which of the following is true of Iteration Goals in SAFe?

  1. They provide KPIs for tracking progress and value realization
  2. They enable teams to keep aligned with PI objectives
  3. They describe the value of planned Features and Enablers
  4. They provide quantifiable metrics to be used in retrospectives

Answer(s): B



Iteration Goals serve what purpose?

  1. To align team members to a common purpose
  2. To define the what, the how, and the how much
  3. To set preliminary PI Objectives

Answer(s): A