Why is a confidence vote held at the end of program increment (Pl) planning?

  1. To build shared commitment to the plan
  2. To remove the risks for the Pl
  3. To ensure the business owners accept the plan
  4. To hold the teams accountable if the Agile release train (ART) does not deliver on its commitment

Answer(s): A



What are two outputs of Iteration Planning? (Choose two.)

  1. PI Objectives
  2. Iteration goals
  3. Team Backlog
  4. Iteration backlog
  5. Program Backlog

Answer(s): B,D



Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)

  1. Provide a team vision
  2. Encourage continuous learning
  3. Encourage skill specialization
  4. Ensure time is allocated for innovation and planning
  5. Facilitate conflict

Answer(s): B,D



What is one way to secure stakeholder commitment to the Agile Release Train?

  1. Provide them a planning schedule outlining a five-year plan for development
  2. Have them estimate User Stories for the teams
  3. Send them the Program Increment (PI) Objectives after each PI Planning event
  4. Have them attend the Program Increment (PI) Planning event

Answer(s): D



What is the main reason why some teams never reach Stage 4 (Performing) in the stag-es of high performing teams?

  1. Because leadership is spontaneous
  2. Because the team is not structured correctly
  3. Because there are conflicts
  4. Because no one guides them

Answer(s): D