During the management review and problem-solving meeting, one team raises the risk of not finishing a Feature before the end of the Program Increment (PI). How can the man-agement team help ensure they complete the Feature within the PI?

  1. Use buffer resources as a guard band
  2. Redefine the definition of done for Features
  3. ROAM the risk appropriately
  4. Negotiate a reduction in scope of the Feature

Answer(s): D



What best describes what stream-aligned teams do?

  1. Analyze value streams and transform them using lean-agile principles
  2. Build and deliver customer value with minimal dependencies on other teams
  3. Promote better flow of communications between leadership, trains and teams
  4. Use process-mapping to identify and eliminate process bottlenecks

Answer(s): B



When should a Product Owner (PO) develop preliminary Iteration Goals?

  1. After PI Planning
  2. During PI Planning
  3. Prior to iteration planning
  4. During backlog refinement

Answer(s): C



What is the recommended duration of an Iteration in SAFe?

  1. Three weeks
  2. Two weeks
  3. Four weeks
  4. Six weeks

Answer(s): B



What are personas?

  1. Descriptions of actual target customers or users
  2. Key end-users the Product Owner leverages for managing the backlog
  3. Fictional representations of target customers or users

Answer(s): C