Which two actions can be taken immediately during the management review and prob-lem-solving meeting? (Choose two.)

  1. Change the business priorities
  2. Recognize the team with the highest velocity
  3. Combine teams to increase velocity
  4. Change the scope
  5. Hire new people

Answer(s): A,D



SAFe is based on four primary bodies of knowledge which include Agile development, systems thinking, DevOps, and what type of product development?

  1. Incremental product development
  2. Adaptive product development
  3. Lean product development
  4. Iterative product development

Answer(s): C



What does assigning business value to a team's Pl Objectives influence?

  1. How teams plan the implementation
  2. How the Kanban work in process limits are set
  3. How to achieve objectives

Answer(s): A



What can a Release Train Engineer use to support relentless improvement for the Pro-gram Increment?

  1. Inspect and Adapt event
  2. Iteration retrospective
  3. Product Owner sync
  4. Release management meeting

Answer(s): A



What are two anti-patterns for the IP Iteration? (Choose two.)

  1. To minimize lost capacity when people are on vacation or holidays
  2. To plan work for the IP lteration during P Planning
  3. To allow for sufficient capacity in the Program Roadmap
  4. To wait for the IP Iteration to fix defects
  5. To ensure all Stories and teams' Pl plans are completed prior to the IP Iteration

Answer(s): B,D



Viewing page 4 of 37
Viewing questions 16 - 20 out of 219 questions