Which SAFe Core Competency incorporates guidance on coordinating trains and suppli-ers?

  1. Enterprise Solution Delivery
  2. Business Agility
  3. Measure and Grow
  4. Lean Portfolio Management

Answer(s): A



How are the 5 Whys used?

  1. To coach a team through powerful questions
  2. To brainstorm ideas
  3. To define acceptance criteria for a Story
  4. To identify a root cause(s) of a problem

Answer(s): D



Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication.
What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)

  1. Organizational readiness - Strategic alignment; roles, teams, and train setup
  2. Architectural readiness - Defining the Architectural Runway
  3. Operational readiness - Facilitating PI events such as scrum of scrums, Iteration Planning, and System emo
  4. Facilities readiness - Space and logistics for the event
  5. Process readiness - The operational rhythm that enables SAFe governance

Answer(s): A,D



During which part of an Inspect and Adapt event would differences between planned business value and actual business value be presented?

  1. Retrospective
  2. Problem-solving workshop
  3. Quantitative and qualitative measurement
  4. PI system demo

Answer(s): C