A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)
Answer(s): A,B,D
The correct answers are A, B, and D, because these techniques would be most helpful in this situation. Consulting with the Development Team may help identify the root causes of the impediments and possible solutions. Prioritizing the list and working on them in order may help reduce the backlog and focus on the most important or urgent issues. Alerting management to the impediments and their impact may help escalate the problems and get support from the organization.
A product Increment must be released to production at the end of each Sprint.
Answer(s): B
The correct answer is B, because a product Increment does not have to be released to production at the end of each Sprint. The Scrum Guide states that "at the end of a Sprint, the new Increment must be `Done, ' which means it must be in useable condition and meet the Scrum Team's definition of `Done'. An increment is a body of inspectable, done work that supports empiricism at the end of the Sprint. The increment is a step toward a vision or goal." Therefore, a product Increment must be potentially releasable, but the decision to release it is up to the Product Owner.
If burndown charts are used to visualize progress, what do they track?
Answer(s): C
The correct answer is C, because if burndown charts are used to visualize progress, they track work remaining across time. A burndown chart is a graphical representation of the amount of work left to do versus the time available. It helps the Scrum Team monitor and forecast the progress toward the Sprint Goal.
How is management external to the Scrum Team involved in the Daily Scrum?
According to the Scrum Guide1, the Daily Scrum is an event for the Developers of the Scrum Team. The purpose of the Daily Scrum is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work. The Daily Scrum optimizes the probability that the Developers will meet the Sprint Goal. Every day, the Developers should understand how they intend to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint. Management external to the Scrum Team is not involved in the Daily Scrum, as they may interfere with the self-management and empowerment of the Developers.
Scrum Guide
To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.
Answer(s): A
According to the Scrum Guide1, Scrum does not require or provide any specific techniques or methods for product definition. Rather, Scrum provides a framework with roles, rules, and events within which complex products can be developed. To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.