Which of the following best describes an increment of working software?

  1. A decomposition of all Product Backlog items into tasks for future Sprint Backlog lists.
  2. Additional features in a usable state that complement those delivered in previous iterations.
  3. A new user interface design for functionality delivered in previous iterations.
  4. An automated test suite to verify functionality delivered in previous iterations.
  5. UML diagrams that describe how to deliver functionality in future iterations.

Answer(s): B

Explanation:

According to the Scrum Guide1, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, the best description of an increment of working software is additional features in a usable state that complement those delivered in previous iterations.


Reference:

Scrum Guide



In order to achieve the benefits of Scrum, it is important to enact the value of commitment.
What two actions demonstrate the commitment of Scrum Team members? (Choose two.)

  1. Always deliver the items in the Sprint forecast.
  2. Help the other Scrum Team members.
  3. Do your best
  4. Send out a daily status report.
  5. Work late.

Answer(s): B,C

Explanation:

According to the Scrum Guide1, there are five values that guide decisions within Scrum teams:
Commitment
Focus
Openness
Respect
Courage
In order to achieve the benefits of Scrum, it is important to enact these values. Two actions that demonstrate the commitment of Scrum Team members are:
Help the other Scrum Team members, as they work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint. Do your best, as they strive to deliver a potentially releasable Increment that meets the definition of "Done" and provides value to the stakeholders.



The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

  1. False.
  2. True, accordingly to what was committed to the stakeholders.
  3. True, but only after confirmation by the resource manager that the Team has enough capacity.
  4. True.
  5. False, the Scrum Master does that.
  6. False, capacity and commitment are the Project manager's responsibility.

Answer(s): A

Explanation:

The correct answer is A, because the Product Owner does not determine how many Product Backlog items the Development Team selects for a Sprint. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Development Team can assess what it can accomplish over the upcoming Sprint." Therefore, the Development Team is responsible for choosing the scope of work for a Sprint.



Which three of the following are feedback loops in Scrum? (Choose three.)

  1. Sprint Review.
  2. Release Planning.
  3. Sprint Retrospective.
  4. Refinement Meeting.
  5. Daily Scrum.

Answer(s): A,C,E

Explanation:

The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the Scrum Team to inspect itself and create a plan for improvements. The Daily Scrum is a feedback loop that allows the Development Team to inspect its progress and plan its work for the next 24 hours.



When a Development Team is having trouble delivering a working Increment because they don't understand a functional requirement, what should they do?

  1. Add a specialist to the Development Team.
  2. Partially complete the functionality, and discuss the remaining work at the Sprint Review.
  3. Collaborate with the Product Owner to determine what is possible and acceptable.
  4. Defer the work to a more appropriate Sprint.

Answer(s): C

Explanation:

The correct answer is C, because when a Development Team is having trouble delivering a working Increment because they don't understand a functional requirement, they should collaborate with the Product Owner to determine what is possible and acceptable. The Scrum Guide states that "the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team. How this is done may vary widely across organizations, Scrum Teams, and individuals." Therefore, the Product Owner should clarify the functional requirement and negotiate the scope of work with the Development Team.



Viewing page 18 of 55
Viewing questions 86 - 90 out of 298 questions