The Scrum Master is responsible for the process in which Scrum is adopted and enacted.

  1. True
  2. False

Answer(s): A



As a Scrum Master, you observe that the Product Owner is not collaborating with the Development Team effectively. What action would you take?

  1. Send the Product Owner to training.
  2. Nominate a proxy Product Owner.
  3. Act as the go-between.
  4. Coach the Product Owner.

Answer(s): D

Explanation:

A Scrum Master coaches those inside and outside the team on the values of Scrum and incremental delivery.



A Scrum Master teaches those who are interested in the Development Team’s progress that progress in Scrum comes from inspecting an Increment at the Sprint Review.

  1. True
  2. False

Answer(s): A

Explanation:

Working software is the primary measure of progress.



What is the most appropriate action for the Scrum Master to take if the Product Owner is having difficulties managing the Product Backlog?

  1. Have the Development Team order the work instead of the Product Owner.
  2. Have the Product Owner order the items based on size, having the Development Team work on the smallest items first.
  3. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize the flow of value.
  4. Delegate the work to the Assistant Product Owner.
  5. Delay the Sprint in order for the Product Owner to have enough time to prioritize the Product Backlog.

Answer(s): C

Explanation:

The Product Owner’s primary concern is the flow of value reflected in the ordering of the Product Backlog.