Free CIS-PPM Exam Braindumps (page: 10)

Page 10 of 28

Where can a user export project data in either a MPP, XML or CSV format?

  1. Demand Form
  2. Related lists
  3. Project Workbench
  4. Planning Console

Answer(s): D



Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

  1. If the project state is On Hold, actual start date and actual end date are displayed.
  2. If the project state is Pending or Open, planned start date and planned end date are displayed.
  3. If the project state is Draft, actual start date and actual end date are displayed.
  4. If the project state is Work in Progress, actual start date and planned end date are displayed.

Answer(s): B,D



Which of the following states appear in the process flow indicator at the top of the Demand form by default? (Choose three.)

  1. Draft
  2. Approved
  3. Updated
  4. Screening
  5. Deferred

Answer(s): A,B,D



Where are CAPEX and OPEX targets set for each fiscal year?

  1. Demand Workbench
  2. Cost Plans
  3. Portfolio Target
  4. Program Workbench

Answer(s): C



Page 10 of 28



Post your Comments and Discuss ServiceNow® CIS-PPM exam with other Community members:

John commented on February 15, 2024
Question 1 is B - Auto Business Rule for Assessments NOT D Create onDemand Assessment Creates assessments for authorized users after a demand has moved from the submitted state to the screening state. Update Demand State Updates the demand state to Qualified after all assessments are completed. For example, Risk must be between 0 and 10 or Strategic Alignment must be between 0 and 10. Validate Assessment Metrics for Demand Validates the score values for a demand to be within the maximum and minimum values. Auto Business Rule for Assessments Checks if the assessable record exists for the demand and creates an assessable record if none exists.
CANADA
upvote

anon commented on October 15, 2023
q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES
upvote

anon commented on October 15, 2023
Q55- the RIDAC workflow can be modified using Flow Designer, correct answer is D not A
UNITED STATES
upvote

anon commented on October 14, 2023
question 31 is wrong- a new demand is saved in Draft state, not Qualified. Answer should be C not D
UNITED STATES
upvote