A project expense line is a cost associated with a specific source. Examples of specific sources could include: (Choose three.)

  1. User.
  2. Configuration Item (CI).
  3. Project.
  4. Demand.
  5. Fixed Asset.

Answer(s): A,B,E



Which roles can modify agile properties? (Choose two.)

  1. it_pps_admin.
  2. product_owner.
  3. admin.
  4. scrum_master.

Answer(s): A,C



In the base system, what is the default number of cards that can be displayed in the project workspace?

  1. 200
  2. 10
  3. 1500
  4. 1

Answer(s): A



Demand managers can enhance a demand request by adding the following: (Choose three.)

  1. Requirements
  2. Change Requests
  3. Problems
  4. Decisions
  5. Stakeholders

Answer(s): A,D,E



This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.

  1. Project form.
  2. Stakeholder registry.
  3. Demand form.
  4. Application registry.

Answer(s): B