Why might you want to consider a staged, or incremental, implementation of a given architectural work package?

  1. To manage the impact of a large architectural change on the user community.
  2. Because adequate skilled resources are not available.
  3. All of these
  4. To allow sufficient time to do a gradual migration from a legacy system.
  5. To mitigate the risks of failure if the implementation project encounters difficulties.

Answer(s): C



Which of the following is not an appropriate consideration in Phase F - Migration Planning?

  1. Geographic separation for staged deployments
  2. Costs and benefits
  3. Retraining the user community
  4. Choice of application platforms
  5. Resourceavaiability

Answer(s): D



Which of the following is not typically part of the implementation recommendations that would be included in the Impact Analysis for Phase G?

  1. Architecture Building Blocks
  2. Criteria for measuring the success of the projects to be implemented
  3. Analysis of risks related to the implementation
  4. Specific details about the solution building blocks
  5. Other issues to be brought to the attention of the implementation governance body

Answer(s): A



Which of the following is not a key input into Phase G - Implementation Governance?

  1. Statement of architecture work
  2. Competitive analysis reports
  3. Request for architecture work
  4. Reusable solution building blocks
  5. Impact analysis

Answer(s): B