Free LEED-AP-ID-C Exam Braindumps (page: 6)

Page 5 of 26

Which of the following must be considered in order to meet Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management if the tenant requires 24-hour cooling in a server room?

  1. Base-building chiller specifications
  2. CFC-free refrigerants in tenant cooling units
  3. Temperature monitoring of building cooling water
  4. ENERGY STAR® compliant cooling units with low CFCs

Answer(s): B



A tenant with 1,000 employees wishes to pursue LEED Interior Design and Construction Certification for their space in which they will be the sole tenant.
Which of the following building attributes will help the tenant achieve points in the Location and Transportation category?

  1. A car sharing program
  2. 60 bike racks and seven shower/changing rooms
  3. Electric car charging stations in the parking garage
  4. A bus line with 30 daily rides with a bus stop within 1/2 mi. (0.80 km) of the building entrance

Answer(s): B

Explanation:

To comply with the Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management, especially for a server room that requires 24-hour cooling, it's essential to use refrigerants that have no ozone depletion potential and low global warming potential. CFC-free refrigerants in tenant cooling units are necessary to meet this prerequisite, as they minimize the environmental impact of the refrigerants used.


Reference:

The LEED reference guide for Interior Design and Construction outlines the requirements for the Fundamental Refrigerant Management prerequisite. It specifies that projects must not use CFC-based refrigerants or must plan to phase out such refrigerants in favor of alternatives with lower environmental impact.



If the client has purchased green power that is not Green-e certified, then the project team should

  1. accept not earning Energy and Atmosphere Credit, Green Power
  2. provide documentation as to how the green power is equivalent to Green-e certified
  3. apply for an Innovation Credit and explain the situation in a narrative
  4. apply the percentage to Energy and Atmosphere Credit, Renewable Energy Generation

Answer(s): B

Explanation:

When green power is not Green-e certified, the project team can still pursue the Energy and Atmosphere Credit for Green Power by demonstrating that the purchased green power meets equivalent standards. This involves providing documentation that verifies the green power's quality and production process align with the criteria set by Green-e certification.


Reference:

The LEED v4 Reference Guide for Interior Design and Construction includes provisions for using green power that is not Green-e certified, as long as the project team can substantiate its equivalence. This can be done through third-party verification and ensuring that the energy source meets the requirements for renewable resources detailed in the current version of the Green-e standard.



Discussing the project goals to help identify the credits and options that the team should attempt is an example of

  1. documenting LEED credits
  2. creating the Basis of Design
  3. developing the LEED Scorecard
  4. implementing the Commissioning Plan

Answer(s): C

Explanation:

The process of discussing project goals to identify the credits and options that the team should attempt aligns with the development of the LEED Scorecard. The LEED Scorecard is a tool used to track the credits pursued and points earned by a project, guiding the team in selecting the most appropriate and beneficial credits to achieve their sustainability objectives.


Reference:

LEED v4: Interior Design + Construction Guide2
LEED scorecard overview and resources1






Post your Comments and Discuss US Green Building Council LEED-AP-ID-C exam with other Community members:

LEED-AP-ID-C Discussions & Posts