Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  1. Multiple calendars.
  2. Start and finish constraints.
  3. Preferential logic.
  4. Front end loading.

Answer(s): D



You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  1. Not suitable for complicated projects with multiple planned critical paths.
  2. Accuracy is increased by inserting delaying events into the as-planned schedule.
  3. Not suitable for projects with long durations.
  4. Less accurate as the analysis advances through the project.

Answer(s): B



Which statement is true?

  1. Where compensability cannot be established, excusability is assumed.
  2. Where compensability can be established, excusabltity cannot be assumed.
  3. Where compensability cannot be established, excusability is a given.
  4. Where compensability can be established, excusability is assumed.

Answer(s): A



Which of the following phases does NOT describe the commonly accepted construction life cycle?

  1. Claims and disputes phase.
  2. Installation phase.
  3. Planning and design phase.
  4. Turnover and start-up phase.

Answer(s): C