Free AACE-PSP Exam Braindumps
Planning & Scheduling Professional (PSP) Questions 89–96 (page: 13)

Updated On: 15-Jun-2026

Activity C is a

  1. Contentious activity.
  2. Continuous activity.
  3. 1-day activity.
  4. Milestone.

Answer(s): D



What is the remaining work duration of Active D?

  1. 4.
  2. 11
  3. 8.
  4. 3.

Answer(s): C

Explanation:

Understand the Relationship Between G and H:
The time-scaled diagram shows that Activity H starts immediately after the finish of Activity G.
This is indicative of a Finish-to-Start (FS) relationship.
Cross-Verification:
Option A: Incorrect. The relationship is visible in the diagram.
Option B: Incorrect. There is no evidence of a Start-to-Start (SS) relationship.
Option D: Incorrect. Finish-to-Finish (FF) is not applicable here.
Option C: Correct. FS relationship matches the network logic.



What is the relationship depicted between Activity G and Activity H?

  1. You cannot tell with the supplied information.
  2. Start-to-start.
  3. Finish-to-start.
  4. Finish-to-finish.

Answer(s): B



What does the narrow band at "Y" represent?

  1. Resource limitation period.
  2. A rework period.
  3. Activity inactivity.
  4. You cannot tell with the information supplied.

Answer(s): A

Explanation:

Interpret the Narrow Band at "Y":
The narrow band at "Y" is located on a part of the schedule where activities have been delayed or slowed down.
Such delays typically indicate resource limitations (e.g., insufficient manpower or equipment).
Reasoning:
No evidence of rework or activity inactivity is explicitly shown in the diagram.
Resource limitations are common in network diagrams to explain such periods.
Cross-Verification:
Option B: Incorrect. No evidence of rework exists.
Option C: Incorrect. Activity inactivity does not fit the context.
Option D: Incorrect. Sufficient information is provided.
Option A: Correct. Resource limitation fits the observed diagram behavior.



What is the actual duration as of the status date or data date of Activity B?

  1. 7.
  2. 3.
  3. 0.
  4. 4.

Answer(s): A

Explanation:

Understand Activity B's Status:
Activity B has an original duration of 5 days.
As of the data date/status date, the diagram shows progress beyond 5 days.
Review Actual Duration:
The progress bar indicates that 7 days have already been worked on Activity B.
Actual duration as of the status date = 7 days.
Cross-Verification:
Option B: Incorrect. Progress exceeds 3 days.
Option C: Incorrect. Progress is not 0 days.
Option D: Incorrect. Progress is more than 4 days.
Option A: Correct. Matches the observed progress on the diagram.


Reference:

PSP Study Guide (2019), Section on Network Diagrams and Status Updates.
AACE Recommended Practices, RP 10S-90.



Which activity is drawn in the incorrect position?

  1. Activity G.
  2. Activity E.
  3. Activity
  4. Activity

Answer(s): B

Explanation:

Position Analysis:
Activity C (Develop Draft Plans and Specifications) has a duration of 5 months and is preceded by Activity A.
The diagram positions Activity C incorrectly since it starts simultaneously with Activity B, but Activity C should start after the completion of Activity A.
Cross-Verification:
Based on the dependencies, Activity C’s incorrect positioning violates the logical sequencing rule.
Verification with PSP Guidelines: Correct logic representation is critical for network diagrams (Ref: PSP Study Guide, Chapter 2A: Logical Sequencing).



Identify the minimum project duration.

  1. 20 months.
  2. 16 months.
  3. 19 months.
  4. 21 months.

Answer(s): B

Explanation:

Minimum Project Duration Calculation:
The critical path determines the minimum project duration.
Path: A →B →G →H →16 months.
Cross-Verification with Network Diagram:
Other paths have shorter durations or do not impact the overall project finish date.
Verification with PSP Guidelines: Critical path analysis is central to determining project duration (Ref: PSP Study Guide, Chapter 2A: Critical Path Method).



Identify the late finish to develop plans and specs.

  1. 9 months.
  2. 10 months.
  3. 8 months.
  4. 7 months.

Answer(s): B

Explanation:

Late Finish Analysis for Activity C (Develop Plans and Specs):
Activity C duration is 5 months, starting after Activity A (3 months).
Late finish = Early start of successor (Activity E) = 10 months.
Cross-Verification:
Based on backward pass calculations, Activity C must end by month 10 to not delay its successor.
Verification with PSP Guidelines: Late finish values are calculated during backward pass (Ref: PSP Study Guide, Chapter 2A: Backward Pass and Float Calculations).



Viewing page 13 of 28
Viewing questions 97 - 104 out of 216 questions


Post your Comments and Discuss AACE International AACE-PSP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!